Podcast: How too much data, dashboards and RCA complicate reliability strategy
Joe Kuhn, CMRP, former plant manager, engineer, and global reliability consultant, is now president of Lean Driven Reliability LLC. He is the author of the book “Zero to Hero: How to Jumpstart Your Reliability Journey Given Today’s Business Challenges” and the creator of the Joe Kuhn YouTube Channel, which offers content on starting your reliability journey and achieving financial independence. In our monthly podcast miniseries, Ask a Plant Manager, Joe considers a commonplace scenario facing the industry and offers his advice, as well as actions that you can take to get on track tomorrow.
This episode is our rapid-fire series where Joe tackles five diferent scenarios and provides five quick fixes. Listen to Joe discuss the traps of too much data and too weak a culture. First, I make him laugh, but tune in to see which scenario gets Joe all riled up!
Below is an excerpt from the podcast:
AT: Yeah, I'm sure every plant has their own collection of sayings and assumptions. Some are probably based on experience, and some just get repeated so often that they become accepted as fact, even if maybe they're not entirely true. So today we're bringing back one of our favorite formats: reliability myth busters. It's our rapid-fire series where I throw out some common beliefs from plant floor, and Joe decides whether they're myth, reality, or maybe a little bit of both. So, Joe, are you ready to bust some reliability myths?
JK: I'm ready. The big challenge for me is to give a two-minute-or-less answer.
AT: Good luck! So, I got five statements that sound familiar to anyone working in maintenance or operations. And Joe, your job is simple. Tell us fact or fiction and why. All right, scenario number one: Our plant is collecting more operational and maintenance data than ever before. Joe, myth or reality? More data automatically leads to better decisions.
JK: Oh my gosh! Absolutely false. You know, more data can be overwhelming. When I came into organizations, I tried to simplify. Data is good, but more data can just be overwhelming and be a mountain. When you get more data, sometimes you get a lot of outliers, and you'll start chasing these events happen that maybe once in 30 years, once in 25 years, instead of the things that happen, once a month or once every six months. So more data can just be distracting. It can be overwhelming.
The one piece, that would be against what I preached on this channel for a long time—it is more data, but you have to do it. It's observation. Most people, they just operate off KPIs and opinion, and you're going to change what you work on. You will change it if you do observation.
Okay, but be careful collecting more data. It sounds good, but it can be a crutch. It can be something you're doing. It doesn't turn into action on the shop floor.
AT: Okay, that was an easy one. I’ve seen this many times. Plants that are information-rich but insight-poor. Okay, scenario number two. We've got the dashboards everywhere, and nearly all our reliability metrics are green. Joe, myth or reality? If the KPIs are green, the plant is performing well.
JK: You know, now you're getting me mad. I see this all the time, all the time. They have these apps on their phone, and they say it's green, green, green, green, green. And then because, when you first put in these systems, one will turn red, and then four levels higher than you in the organization has this Power BI, and it says, "Hey, this is red. Why is that red? I don't ever want to see this red again." And blah, blah, blah, blah, beating on, "Oh, well, we'll throw out the outliers. We'll redefine what's red and green and yellow," and it never happens again.
Boy, you show me how I'm measured, and you can see how I'm going to perform and what's important to me. I am very cautious. Very cautious. I mean, I've seen those dashboards do far more harm than good, especially as you go up in the organization.
Especially as you go—boy, I’ve got a short story. I'll give a short story on this one. My boss called me one time and said, "Hey, you know this piece of equipment's been down for two hours. What's going on, Joe?" Because his dashboard turned red that it's been down for two hours. He asked me what's going on, and I said, "I don't know." And he goes, "Well, don't you think you should know?" And I go, "No." I said, "I had a maintenance supervisor out there. I had a production supervisor out there. I had a maintenance superintendent and production superintendent and head of engineering. If they need me, they'll call me."
Now, I had 30 years in when I told them that. What would a untenured employee or a new employee, a two-year employee, have done? They would have said, "Oh my gosh! First of all, change the color code so that never happens again," and then they focus on knowing everything about the process all the time.
Well, then I'm not working strategically. Dashboards, they've been a net negative at organizations.
More Ask a Plant Manager episodes:
- What are the biggest maintenance shortcuts and why is culture to blame?
- Fact or fiction? The truth about reliability and what plant managers get wrong
- The warning signs of a broken reliability culture and how plant leaders can fix it
- Reliability reality check—why more PMs and high wrench time don’t guarantee reliability
- How to spot fake reliability programs and insights on maintenance execution and culture
- Maintenance vs. operations—Improving communication through shop floor accountability
- Unleash your planner—Turning overwhelmed maintenance planners into strategic leaders
- From burnout to breakthrough—how manufacturing leaders can turn New Years’ goals into real reliability gains
AT: Yeah, we have a whole episode way back about all the different ways people can fake their KPIs. So go check it out. All right, scenario number three: Whenever we have a significant failure, we conduct a root cause analysis. Joe, myth or reality: A root cause analysis can solve all reliability problems.
JK: Well, that's a myth. I love root cause analysis, but they can run amok. People say: any downtime over an hour, we're going to do a root cause. Well, then you're doing a root cause twice a day, and you're just piling up data, piling up actions, and nobody does anything with them.
Actions. Actions change the reliability of the equipment, not just doing the root cause. And, so you’ve got to be cautious. I've seen root cause investigations with over 100 action items. Well, they're not going to do 100 things different, and then, the first one is buy a new piece of equipment.
So root cause investigations are great, but you’ve got to narrow it down to, ‘hey, what three actions could we take that'll prevent this from happening, or how could we have known about this earlier? That's why I love predictive technologies. Hey, this equipment's in the process of failing. We got a little time, but how do we, fix it and then put in a small design change to have that never happen again?
But so many organizations, they find out about root cause. They go to some training, and they just overwhelmingly, everything's root cause. But actions are what prevents failures, not root cause investigations.
AT: Yeah, RCA tells you why, but you have to fix the actual problem in your process or practice, or you have the failure again. I’ve heard a lot of people talking about excessive RCAs in their organization and trying to fight about that, but also the idea that some people just accept failures. Well, you know, this pump goes every eight months. We're used to that. That's how it is. Well, should it be failing every eight months? Again, RCA is the answer, not the action that you need to take.
JK: Yeah, absolutely.
AT: So, scenario number four: We're trying to implement some major reliability improvements, but maintenance seem reluctant to embrace the changes. Joe, myth or reality?
JK: That's reality. You look at maintenance and they're resisting, and you’ve got to say, "Well, why are they resisting?" You're going to get resistance anytime you want to change culture. Everybody resists, okay? Because they understand current state.
But maintenance, a couple things. No, it's probably not going to be the first time you tried to improve the culture, and they've been down this road before. There's a trust issue. There are some people, and it's hard to put all maintenance people think this one way. I can't say that, but some people have gotten used to the overtime that maybe unreliability puts in.
You may be going towards root cause analysis, or maybe condition monitoring, where they're using some problem-solving skills, or they're using some new equipment. That means I need to learn something new. I'm not sure I want to learn something new. I’ve been doing this job for 30 years, so there's all kinds of personal impact to changing a reliability culture.
The number one, I would say, is trust that you are going to stick with it, because most of the time, the maintenance people are quickly excited about better planned jobs, better kitted jobs, being able to do precision work. These people went into the crafts because they like equipment to run well. They like to fix it, and they—they want to feel proud of their work.
And I've heard this story four or five times before. And management's always let me down. Why is this time different? So everybody's going to have some resistance to change, and that's why quick wins are so important. Get some quick wins, get some momentum, and you're in sales. You're in sales.
What action did you guys take last week? What is the result? What action did you take six months ago? What has been the result? Hey, this pump that used to fail every six weeks, it's been in place for six months because we RCA'd it and we took these actions. We changed how we rebuild it, and there you go.
AT: And culture always comes back.
JK: Culture, culture, culture, culture is everything.
AT: Scenario number five: When a major breakdown happens, everyone knows who the heroes are—the technicians who stay up late to get the plant running again. Joe, myth or reality? Celebrating emergency heroes improves morale.
JK: It does not improve morale. I still think celebrating the heroes that come in and save the day creatively, you should recognize them, but it should be at least at equal. You’ve got to celebrate the pump that didn't fail. The lady or gentleman that is in the pump rebuild program, and, hey, we normally have 100 pump failures a year, and we've had three.
You've got to celebrate the people that go out on there with their infrared gun and find an anomaly before the failure. You've got to celebrate the people that did the PM with precision and—and balanced the shaft. So whenever you're giving out a compliment to the heroes, make sure you follow that up at the same time. Maybe even two to one with the real heroes.
The real heroes are the ones that fix the problem before you even knew you had a problem. They found the anomaly. They did the work with precision, and it's a thankless job. You’ve got to celebrate those. The mechanics and electricians—they know that. Hey, I prevented this failure, and just point it out. Point it out.
There's a lot of emotion and drama around an unplanned downtime, and this is going to be two days, and it ends up being one day, and everybody's like, great, but there's little emotion around the failure that you didn't have. So management needs to create it.
AT: Yeah, I have to point back to another old episode of ours that we have about that lure of emergency culture, only because it has one of my favorite titles ever, which is, "Why is everyone on the plant floor drawn to a dumpster fire?" I think it's the perfect metaphor for that reactive emergency maintenance culture and the danger that lies there. So check it out.
JK: Everything stems from culture, Anna. I mean, you've hit on it. It's culture is what you're looking for, and that starts with management actions. This took me a lot of years. Took me a couple decades to get here. I thought it was about tools. I thought it was about expectations. It's culture, and that starts with me.
AT: Yeah, and I think one of the other themes I hear, running throughout all of these five scenarios, is that people can mistake activity for progress, and, collecting data isn't the same as using it, or green metrics aren't the same as healthy metrics, whatever your topic may be. And, celebrating heroic recoveries, isn't always the same thing as building that reliability culture. And back to my favorite metaphor, it's just putting a party hat on a dumpster fire. Well, thanks, Joe, for playing along. I really appreciate it.
About the Podcast
Great Question: A Manufacturing Podcast offers news and information for the people who make, store and move things and those who manage and maintain the facilities where that work gets done. Manufacturers from chemical producers to automakers to machine shops can listen for critical insights into the technologies, economic conditions and best practices that can influence how to best run facilities to reach operational excellence.
Listen to another episode and subscribe on your favorite podcast app
About the Author
Anna TownshendAnna Townshend
head of content
Anna Townshend is the chief editor and head of content for Plant Services. She has been a journalist and editor for more than 20 years and joined Plant Services and Control Design as managing editor in June 2020. Previously, for more than 10 years, she was the chief editor of Marina Dock Age and International Dredging Review. In addition to writing and editing thousands of articles in her career, she has been an active speaker on industry panels and presentations, as well as host for Great Question: A Manufacturing Podcast. Email her at [email protected].