Subscribe to the From the Editor RSS feed | Commitment from top management is always important to any initiative, but especially with equipment reliability programs. “If management isn’t asking about how things are going,” warned Weber, “the level of effort and resources expended on the project drops exponentially.” Be sure to keep reliability relevant and demonstrate its effectiveness and impact on profitability with metrics to keep senior leadership from looking for bigger fish to fry. Weber offered some numbers to which plants should aspire.
- Your maintenance costs should be 2-3% of replacement asset value.
- Total maintenance costs should be less than 15% of total manufacturing costs.
- More than 85% of total maintenance should be planned.
- Proactive maintenance should be 75-80%, and reactive maintenance should be only 10-15%.
- For the maintenance trades, wrench time should be greater than 60%.
- Inventory turns should be no more than three per year.
Klaus Blache, PhD, MBA, CPE, is research professor at University of Tennessee College of Engineering and director of the Reliability & Maintainability Center (www.rmc.utk.edu). Along with Weber, he also chaired SMRP for two years, his tenure being in the late 1990s, and shared expertise in one of the conference presentations.
He identified an engaged workforce as one of the top differences between the best plants and the others. “Why are so many lean implementations failing?” he asked. “A lot of that is failure to engage the workforce. Executives see that engaging the workforce will have a big impact, but they get quarterly bonuses based on production. We’re using the wrong KPIs. The best plants have an engaged workforce. You have to change the thinking process of the people for problem-solving and making decisions based on data.”