Powertrain performance reflects the effectiveness of PdM

Powertrain performance echoes effective predictive maintenance management.

By Edward Sullivan and Neville Sachs

1 of 2 < 1 | 2 View on one page

Maintenance efforts for rotating equipment should start long before the hardware makes its way to the plant floor. Consider the chain of logic between performance and predictive maintenance. Competitive manufacturing plants ensure that rotating equipment is capable of performing at the required levels of precision and accuracy. Achieving the required performance level, in turn, demands that the machinery be as reliable as possible when operators call upon it to help convert raw material into finished goods. The degree of reliability evident on the plant floor is a function of your predictive maintenance program. Addressing the following questions can give you an outline for more effective maintenance, improved reliability and reduced life-cycle cost.

When should we start planning the maintenance for a new piece of machinery?
A. Doing this during the planning stages, before the machine is purchased, helps minimize surprises. Of course, you’re going to start with the vendor’s list of recommended spare parts and maintenance practices. Check vendor references and talk to the maintenance managers responsible for the same or similar machines. Ask how actual maintenance schedules compare with the vendor’s recommendations. Ask for any special suggestions and insights into the machine’s reliability and maintenance needs. Then, be sure to use this information for machine justification.

Do predictive maintenance inspections have to start when the machine is new? Why do we have to be concerned about the condition of a brand-new piece of equipment?
A. The simple answer is to be certain you’ve received what you paid for. Check the machine in great detail as soon as it starts. There’s good data that shows 14% of industrial mechanical equipment has a significant defect when installed. Because of errors made before the machine starts, one in seven will probably require major maintenance before achieving 25% of its design life. Ensure that your machinery is installed and operated correctly by using a detailed equipment acceptance inspection (EAI).

Does this require an expensive, out-of-town consultant bearing all sorts of expensive test gear?
A. Well, you certainly should have a qualified person with lots of skill and experience look at the installation. But it doesn’t have to be expensive and you most likely have access to some qualified people, either in-house or at a nearby supplier.

Keep a few points in mind when developing your EAI. First, its detail should be proportional to the machine’s value. For example, a spared, inexpensive pump whose breakdown won’t be costly doesn’t merit spending a lot of time and money on the inspection. But if a failed, inexpensive pump would cause costly collateral damage, conduct a detailed inspection, including motor current analysis, vibration analysis, infrared scanning and other predictive maintenance measures.

The person conducting the inspection should have a background in detailed testing of similar machines. What gets us in trouble isn’t the things we know we don’t know; it’s the things we think we know, but actually don’t. An inspector without a good understanding of how the machine operates shouldn’t be inspecting it.

Don’t make the machine vendor solely responsible for the EAI. Vendors try to do a good job for customers, but inspector loyalty lies with whoever signs their paycheck. If you’re relying on vendor inspection, be certain you’ve got your own skilled people looking over the inspector’s shoulder. Remember, the supplier’s representatives inspected and passed the 14% mentioned earlier.

Our machine is installed; the faults revealed during the EAI were corrected. What long-term predictive or preventive inspections should be planned?
A. Oops! We have to step back to the preplanning phase to analyze what might go wrong with the machine. Then, knowing what to look for, we can plan for the needed people and inspection equipment.

Different machines require different inspections and inspection skills. For example, it’s unlikely that someone who is good at vibration analysis and diagnosis will also be a qualified certified lubrication specialist who is good at motor current analysis. Planning for your inspections means:

Plan to have qualified, certified people conduct them. This might require hiring skilled vendors or having your technicians trained and tested.

Analyze machines to understand whether they should be monitored manually or with factory-installed transducers and the like.

Good grief! This sounds like it’s expensive. Is it really worth it?
A. The answer depends on the cost of a breakdown or a production interruption. Only you know the cost of being unable to supply your customers. Only you can estimate the cost of an environmental incident that an unanticipated breakdown initiates. But several studies have shown that plants with an active PdM program enjoy rotating equipment maintenance costs that are about half of those seen in a reactive plant. Also, the equipment availability in plants using PdM is about 10% higher.

You’ve convinced me that we should have a PdM program. Where and how do I start?
A. The key to any intelligent maintenance program is understanding the cost of maintenance and the cost of not having a machine available. Many maintenance technicians are parts changers, blindly replacing pieces until the machine operates again. In some places, this is acceptable, but in most competitive, lean manufacturing sectors, this approach leads to plant closures.

Look at your equipment history and the costs. Develop a 3 X 3 (or 3 X 4) matrix to determine which machines are most critical and demand the most intense inspection. Whether you do the work or outsource the inspection program, whoever sets it up must know where to start and must understand the criticality of each machine. A guideline frequently used as a starting point is machine speed because faster machines tend to deteriorate faster. You can chart machine speed on one axis against cost or process criticality on the other (Table 1). These values indicate which machines most need an inspection program.

1 of 2 < 1 | 2 View on one page
Show Comments
Hide Comments

Join the discussion

We welcome your thoughtful comments.
All comments will display your user name.

Want to participate in the discussion?

Register for free

Log in for complete access.

Comments

No one has commented on this page yet.

RSS feed for comments on this page | RSS feed for all comments