Streamline shutdowns by integrating planning, scheduling and tracking

Overview:

To keep daily maintenance and shutdowns on track, a nuclear generation facility tightly integrated its scheduling system with its planning and cost-tracking system.

The successful integration contributed to reducing the length of refueling outages from 50 days to the currently-planned 25 days, saving $450,000 per day in lost revenue. When an unplanned outage occurs, the plant can quickly synchronize systems and build an accurate schedule that helps start maintenance work within four to six hours.